Several Greek power units face extended maintenance periods in 2026, with the largest outages concentrated in 2H26, with the 810MW Megalopoli 5, 400MW Elepidison Thess, and 405MW Megalopoli GT unit 2 offline for 90–98 days in 2H, data from IPTO show.
Overall, the first half of the year sees roughly 1.2GW offline, while the second half jumps to over 2GW due to the prolonged maintenance of multiple large units (see chart below).

Find more articles and bullets on these widgets:
The Underlying December contract trades at 124.23.
UBS write “continuous positive price action in equities has been very profitable for CTAs in the last three months. Strong Q3 earnings are not derailing the trend, encouraging CTAs to stay put despite heavy positioning”.
CADUSD (5th Dec) 72.00c, sold at 0.08 in ~1.9k.