EPNG updated its preliminary October 2025 maintenance schedule, showing an average of 5 bcf/d offline for the month
South Mainline’s Ehrenberg compressor station will alone have 1.406 bcf/d reduced on October 21. Ehrenberg is a crucial interstate connection between Arizona and Southern California, with a total 2.059 bcf/d working capacity.