The Freeport LNG terminal in Texas is restarting its train 3, with repairs expected to take place on trains 1 and 2 on a rolling basis until May, sources told Bloomberg.
- Train 3 went offline in late-January to replace an electric motor and is due to restart this week.
- Gas supply had fallen earlier this month, indicating that two trains have been offline, Bloomberg said.
- Once train three comes back online, at least two trains are expected to run through April, before all three trains come online in May, sources told Bloomberg.